Robstown Independent School District

Welcome to Robstown Independent School District. We are #RobstownProud!

Construction Project

February 2017 Update

Construction has been moving along steadily, according to plan. Thus far, 100% of the concrete slab, measuring 39,000 square feet has been poured and completed. Block ‘C’ and Block ‘D’ of the base-bid addition has 40% of the walls erected, which will contain classrooms, an interactive learning center, and restrooms. As of late February, Block ‘C’ and Block ‘D’ are scheduled to be finished in approximately seven weeks. This will include roof structure and walls. On February 27, 2017 the roof structure installation process is scheduled to begin. Approximately 20% of the total project has been completed thus far.

January 2017 Update

In efforts to provide transparent communication with Robstown ISD employees, staff, and community members, we would like to provide monthly updates regarding the Robstown High School additions and renovations project. As of late January, two-thirds of the total concrete slab, measuring approximately 30,000 square feet, has been poured for the base-bid addition. Half of the block walls have been erected and 90% of the site utilities have been completed. Within the next couple of weeks, onlookers will see trusses that are scheduled to be delivered to begin the installation of roof structure processes. Overall, construction has been steadily advancing.