Robstown Independent School District

Welcome to Robstown Independent School District. We are #RobstownProud!  Pk-5 Campuses Driscoll, San Pedro, Ortiz and Lotspeich will be verifying residency and signing up parents for family access  May 23 from 4:00-6:00.  More information under the parent tab.

Construction Project

April 2017 Update

The construction status update brings forth great strides that have been made. ‘Block D’ has had 100% of structural steel and its’ roof installed. Duct, electrical, plumbing, and sprinkler system installations have been finalized with inspections completed for main line utilities. All walls have been sealed, primed, and have had their first coat of paint applied. In ‘Block C’ and ‘Block D’ roof decking is 50% complete. By Mid-May, onlookers can expect painting to be completed. Also, window installation, ceiling grid, and flooring to be near completion. Additionally, exterior brick installation will be started. Overall, about 50% of the total base-bid addition project has been completed. Construction status has been on schedule and no delays have occurred.

March 2017 Update

The construction status update for the month of March yields 100% of walls completed for the base-bid addition project, which includes Block ‘B’, Block ‘C’, and Block ‘D’. Roof structure is 90% complete in block ‘D’. During the first week of April, structural steel beam installation on the roof will begin. Weather permitting, painting will begin in Block ‘D’ over the next two weeks, and is scheduled to be finalized by the end of April. In summation, approximately 35% of the total base-bid addition project has been completed and construction is progressing according to schedule.

February 2017 Update

Construction has been moving along steadily, according to plan. Thus far, 100% of the concrete slab, measuring 39,000 square feet has been poured and completed. Block ‘C’ and Block ‘D’ of the base-bid addition has 40% of the walls erected, which will contain classrooms, an interactive learning center, and restrooms. As of late February, Block ‘C’ and Block ‘D’ are scheduled to be finished in approximately seven weeks. This will include roof structure and walls. On February 27, 2017 the roof structure installation process is scheduled to begin. Approximately 20% of the total project has been completed thus far.

January 2017 Update

In efforts to provide transparent communication with Robstown ISD employees, staff, and community members, we would like to provide monthly updates regarding the Robstown High School additions and renovations project. As of late January, two-thirds of the total concrete slab, measuring approximately 30,000 square feet, has been poured for the base-bid addition. Half of the block walls have been erected and 90% of the site utilities have been completed. Within the next couple of weeks, onlookers will see trusses that are scheduled to be delivered to begin the installation of roof structure processes. Overall, construction has been steadily advancing.